Soar Y Mynydd 11kV Plough Installation

G T Jones Contracting Ltd's first successful trenchless laying project of 3km of 11kV cable on Ceredigion's challenging Cambrian Mountains.

client Icon
CLIENT
location-icon
LOCATION
Ceredigion
categories-icon
SERVICE
Trenchless Cable Laying
completed-icon
COMPLETED
January 2026

Project Overview

G T Jones Contracting Ltd's first successful trenchless laying project of 3km of 11kV cable on Ceredigion's challenging Cambrian Mountains.

Detail

The project comprises the installation of approximately 3 km of 11 kV underground electrical cable across Soar y Mynydd, Ceredigion, using trenchless installation techniques with the Foeck FSP 22 Plough and Foeck FWF 92 Winch, to minimise disturbance to the surrounding landscape, environment and existing land uses.

The project is being delivered within a challenging rural and upland environment, characterised by steep and undulating terrain, difficult ground conditions,  sensitive habitats and potentially variable geology. These constraints require careful planning, specialist plant and equipment, and a construction methodology that can safely and efficiently install the cable while minimising the project's environmental footprint.

Outcomes

  • Ground disturbance significantly reduced and minimal impact on the landscape
  • Improved project efficiency, allowing installation in a shorter timeframe
  • Zero safety incidents and high environmental performance throughout
  • Improved long-term durability and reduced maintenance risk for the client
  • All works delivered on time, and to a high standard

Length

January 2026 - 1 week

Soar Y Mynydd 3km Installation
Scroll to view full comparison
Metric Traditional Open Cut Foeck Plough Estimated Saving Comment
Programme Approx. 30 days 6 days 80% faster 100m/day open cut vs 500m/day ploughing for 3km
Fuel Approx. 6,000L Approx. 540L 91% reduction Open cut = 2,000L/km. Plough = 180L/km
Carbon Approx. 15tCO2e Approx. 1.35tCO2e 91% reduction Based on fuel assumptions using approx. 2.5kg CO2e/L diesel
Excavated spoil Approx. 1,200m³ Near-zero Approx. 100% reduction Works from 400m³/km open cut
Project Highlight

The Foeck Plough allowed a 3km installation to be completed across sensitive rural upland ground with minimal excavation. Due to the environmental sensitivity of the area, including SSSI considerations, a traditional open-cut method may not have been practicable without significant environmental consequences, increased reinstatement and greater disturbance to farmland, peat soils and the surrounding landscape.